Philip S. Miller Park & Field House

Castle Rock, CO

Installed October 2013

Project Overview

Originally designed as a corrugated metal culvert, Turner Construction and Rocky Mountain Excavating worked with JVA Consulting Engineers to provide an aesthetically pleasing precast concrete arch for the new 48-acre park.

Design Functionality

The structure carries the park’s drainage channel and a walkway under a bike and pedestrian path.

Project Team

Owner: Town of Castle Rock, CO

Architect: BHA Design Inc.

Engineer: JVA Consulting Engineers

Contractor: Turner Construction / Rocky Mountain Excavating, Inc.

Precast Producer: Lindsay Precast – Firebaugh Division

Technical Details

Span: 32 ft

Rise: 11 ft

Length: 48 ft

Cover: 3 ft 6 in

Live Load: HL-93

Skew: None

Type: Arch-Box